PROPERTY

Pacific House


CLIENT

CLS Holdings PLC


ACHIEVEMENTS

Successful replacement of both the Landlord’s main incoming low voltage switch panels was achieved over two weekend shutdown periods. Meticulous advanced surveys, logistical planning and off-site testing was key to the successful outcome of this project with emphasis on contingency back-up planning to cover all eventualities. Temporary generator back-up power was introduced to maintain critical services in the building whilst the works took place. The replacement switch panels now provide the property with improved system resilience and modern circuit protection in full compliance with current BS EN standards.


The project comprised of our Project Team undertaking the production of a Technical Performance Specification, a JCT Design and Build Contract, competitive tendering of the Works, full tender analysis of submissions, recommendation for Contractor award and full Project Management of the works including witnessing and final snagging.

Get in Touch